| Task | Schedule | ||
|---|---|---|---|
| Dates: |
|
||
| Work on Views |
67%
|
||
| Work on Filters |
20%
|
||
|
Milestone 1 |
|||
| Backend Integration |
10%
|
||
|
Milestone 2 |
|||
| Performance |
|
||
| Testing |
|
||
|
Milestone 3 |
|||
|
CAT |
| Milestone | Date | Notes |
|---|---|---|
| Milestone 1 | 16 Jan 2004 | View and Filters are fully working. |
| Milestone 2 | 30 Jan 2004 | The backend is entirely integrated. New features MUSN'T be added. |
| Milestone 3 | 13 Feb 2004 | Testing and working on performance has been done. Fix as many bugs as possible! |
| CAT | 14 Feb 2004 | Client Acceptance Test at Wacker in Munich |
| Name | Progress | Start | End | Work | Resources | Notes | ||
|---|---|---|---|---|---|---|---|---|
| Work on Views | 67% | 2004-01-12 | 2004-01-16 (12:00) | 5d 15h | ||||
| Work on Filters | 20% | 2004-01-12 | 2004-01-16 (12:00) | 5d 15h | ||||
| Milestone 1 | 2004-01-16 15:00 | |||||||
| Backend Integration | 10% | 2004-01-18 (09:00) | 2004-01-30 (18:00) | 11d 6h | ||||
| Milestone 2 | 2004-01-30 18:00 | |||||||
| Performance | 0% | 2004-02-01 (09:00) | 2004-02-06 (18:00) | 5d 15h | Performance of the entire UI should be improved. | |||
| Testing | 0% | 2004-02-08 (09:00) | 2004-02-13 (18:00) | 5d 15h | Testing Sessions have started | |||
| Milestone 3 | 2004-02-13 21:00 | |||||||
| CAT | 2004-02-14 09:00 | |||||||
| Name | Type | Tasks | |
|---|---|---|---|
| Alexander Duggleby | Worker | duggleby@in.tum.de |
|
| Anja Rein | Worker | rein@in.tum.de |
|
| Christian Meyer | Worker | meyerc@in.tum.de |
|
| Jian Zhu | Worker | zhu@in.tum.de |
|
| Mario Ullrich | Worker | ullrichm@in.tum.de |
|
| Michael J. Huber | Worker | hubermic@in.tum.de |
|